Resource Usage Report (Report, Workload, Resource Usage) is showing dates of
11/109 to 1/31/10 on the report. Why is it limiting itself to those dates?
Very odd.

Thank you so much for your help!
Stacey
 
D

Dale Howard [MVP]

Stacey --

By default, Microsoft Project prints the default reports using the date
range from the Start date of the project to the Finish date of the project.
The only way to change this is in the Print dialog, where you can change the
date range for printing in the Timescale section of the dialog. Do either
of these explain what you are seeing? Let us know.
 