MSP2K - Summary Row 0 does not show all the dates

G

ggreensp

When using the Project summary task row 0, the data from
some of the columns do not get updated from the subtasks

The fields are displayed as NA


Why does the fields not get updated?
Anyway to force the fields to update?
 
G

ggreensp

The fields that do not display are the following

Baseline dates and Interim plan dates:

Baseline start/Baseline finish
Start1/Finish1

We use these fields to baseline our 75% commit dates (Baseline Start/Finish)
and our 90% commit dates (Start1/Finish1) Recommited 90% commit dates
are in the Start2/Finish2 fields.

We have found that the Project Summary field does not display the dates from
these columns. And since these fields are pulled into the PWA Project
Center view - all the dates are set to NA.

And another issue - which Microsoft had not been able to correct is that the
baseline fields and start1/finish1 column headers cannot be displayed on the
PWA.
 
D

Dale Howard [MVP]

ggreeensp --

How are you saving your baseline and interim plan dates in the project? Are
you selecting the All Tasks option in the Baseline dialog, or are you
selecting specific tasks and then selecting the Selected Tasks option?

I'm not sure what behavior you are describing in PWA, as I have no trouble
getting the fields in question to display in PWA. Please say more about
your problem. Thanks!
 
Top