B
Betsy Hada
I have a plan with hour-by-hour tasks, for a computer installation weekend.
Half of my team can't "figure out" the difference between the stated times
(all Eastern Standard) and "their" timezone, which is Pacific. Is there any
way in Project for me to use "Start1" and "Finish1" to subtract 3 hours from
the existing "Start" and "Finish" times?
Can I do this via a formula? If so, what syntax would I use for the formula?
I've tried:
[Start] -3h
[Start] - 3 hours
[Start] - 3h
none of which has worked. When I put in "[Start] -3" (which is the only
permutation Project wanted to accept) and clicked "OK", the times shown in
that column are exactly the same as in the "Start" field.
Thanks in advance!
Betsy, Frazzled PM
San Francisco Bay Area
Half of my team can't "figure out" the difference between the stated times
(all Eastern Standard) and "their" timezone, which is Pacific. Is there any
way in Project for me to use "Start1" and "Finish1" to subtract 3 hours from
the existing "Start" and "Finish" times?
Can I do this via a formula? If so, what syntax would I use for the formula?
I've tried:
[Start] -3h
[Start] - 3 hours
[Start] - 3h
none of which has worked. When I put in "[Start] -3" (which is the only
permutation Project wanted to accept) and clicked "OK", the times shown in
that column are exactly the same as in the "Start" field.
Thanks in advance!
Betsy, Frazzled PM
San Francisco Bay Area