David --
To view multiple baselines simultaneously, you would need to create some new
Tables for this purpose. In fact, for this purpose I would recommend that
you do the following:
1. Make a copy of the Cost table (do not modify the default Cost table)
2. Give the copy a unique name, Baseline Cost Comparison
3. Remove all of the cost-related columns other than the Baseline Cost
field
4. Add all of the baseline cost fields you are using, such as Baseline1
Cost, Baseline2 Cost, etc.
Once you have done this, you can also complete similar steps to create a
custom Baseline Work Comparison table by making a copy of the Work table,
and to create a custom Baseline Date Comparison table by making a copy of
the Variance table. Just a thought, and I hope it helps.