Sam --
Multi-value outline codes are only available for Enterprise Resource Outline
Code #20-29 fields. There are 10 of these total. It is not possible to set
up multi-value Project or Task fields. To set up one of these resource
fields as a multi-value field, you need not do anything special when setting
up the values in the field itself. Simply open the Enterprise Global and
set up the values in the field the way you would normally do. Once you have
completed this process, save and close the Enterprise Global, then close
Microsoft Project.
Now open Microsoft Project again and log into Project Server so that you get
the latest changes to the Enterprise Global. To specify mutliple values in
the field, open the Enterprise Resource Pool and double-click on each
resource's name. In the Resource Information dialog box, on the Custom
Fields page, you will specify the initial value for each multi-value field
plus any additional values you desire using checkboxes. It will be obvious
how to do it. Hope this helps.
--
Dale A. Howard
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"