I
IbanezJem
Part One: When filling out the Project Web Access (PWA) Timesheets:
If a task has not received all the necessary hours allocated to it by a
deadline, the task end date on the timeline gets pushed out to accommodate
for this. Even if the end date was constrained “Must Finish Onâ€/â€No Later
Thanâ€, the task end date moves out.Is there a way to keep the task bar from
extending? For instance, the Overall Project Summary Bar which shows the end
of a project should not move.
Part Two: Administrative Projects
Can anyone point to a link that work, for the best way to set these things
up?
Part Three: Creating Projects
When saving directly to the server, some functionality seems to be lost and
we do not understand why.
1) In PWA’s Project Center, after clicking on a project, a detailed view of
the project is not created.
2) Cannot add yourself to an Existing Task.
Portfolio Analyzer:
In PWA, why can't a user with admin privs get into Portfolio Analyzer
(Admin, Manage Views, Add, Portfolio Analyzer)? SQL privs seem to be fine
Thanks in advance!
If a task has not received all the necessary hours allocated to it by a
deadline, the task end date on the timeline gets pushed out to accommodate
for this. Even if the end date was constrained “Must Finish Onâ€/â€No Later
Thanâ€, the task end date moves out.Is there a way to keep the task bar from
extending? For instance, the Overall Project Summary Bar which shows the end
of a project should not move.
Part Two: Administrative Projects
Can anyone point to a link that work, for the best way to set these things
up?
Part Three: Creating Projects
When saving directly to the server, some functionality seems to be lost and
we do not understand why.
1) In PWA’s Project Center, after clicking on a project, a detailed view of
the project is not created.
2) Cannot add yourself to an Existing Task.
Portfolio Analyzer:
In PWA, why can't a user with admin privs get into Portfolio Analyzer
(Admin, Manage Views, Add, Portfolio Analyzer)? SQL privs seem to be fine
Thanks in advance!