In order to maintain multiple administrative project plans
related to the corresponding dept & have all the
enterprise resources assigned to these tasks. Is it
possible to have the tasks at 0 days & all the resources
assigned to 0hrs, units as 0%? As the resources fill in
their timesheet the task duration will get adjusted. The
projects are kept at Fixed duration & not effort driven.
This is to enable resource availability as resources will
not be booked to these Administrative Projects.
Please advise....
Regards,
David
related to the corresponding dept & have all the
enterprise resources assigned to these tasks. Is it
possible to have the tasks at 0 days & all the resources
assigned to 0hrs, units as 0%? As the resources fill in
their timesheet the task duration will get adjusted. The
projects are kept at Fixed duration & not effort driven.
This is to enable resource availability as resources will
not be booked to these Administrative Projects.
Please advise....
Regards,
David