Someone knows how to use Multiple approval feature in 2003 ?


What did I forgot ?

- I have a RBS
- the ressource manager is at a upper level than the ressource
- I chosed "Approve ressources timesheet" in categories for my ressource
managers

I can't get the "Approve timesheets" and "View Timesheet summary" menu in
Ressource of PWA

Nota : I have no problem for "adjust actual" menu

Thanks so much
Jean-Luc
 
D

Dale Howard [MVP]

Jean-Luc --

Do the following:

1. Log into PWA with Administrator permissions
2. Click the Admin menu
3. Click the Server Configuration link
4. Scroll down to the "Select the features..." section
5. Scroll down the list of features to the Tasks section
6. Enable the "Approve Timesheeets for Resources" and "Timesheet Approval"
options
7. Click the Save Changes button

In Step #6, those two features are disabled by default. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 
J

Jean-Luc.chantry

Thanks so much Dale,
And so sorry to have forgotten that upper level of configuration