Multiple Calendars and Non Working time

A

Andy Maharaj

Hello,

How on the Gantt chart view do I show the correct Non
working time on 2 activities that have two different Task
Calendars?

Thank You

Andy Maharaj
 
S

Steve House

You really can't - the nonworking time displayed on the Gantt timescale
is a global setting - you can change it for different views and reports
but whatever you select will be applied to all tasks.
 
Top