Ionut said:
How can I apply one cost table to more than one resource - in a single move?
Thank you.
Ionut Lambrescu
Ionut,
I assume you are using a cost rate table other than "A", which is the
default. You can quickly apply the same cost rate table to multiple
assignments by showing either the Task Usage or Resource Usage views.
Add the Cost Rate Table field as a column, select the table, and then do
a fill down as appropriate. If necessary, you can apply a filter to
select certain assignments before doing the fill down.
This probably doesn't qualify as a "single move" but hope it helps.
John
Project MVP