S
scott_hanebutt
I have been doing a lot of reading on Project can came up with a hypothetical
scenario and would like to know how it should be handled.
Sopose someone is writing a book and someone else is editing it and that
editing it will take 1/2 as long as writing it does.
Obviously you can't start editing until you start writing making it a
start-to-start relationship. Just as obviously you can't finish editing
until you finish writing making it a finish-to-finish relationship.
It seams to me that neither one of these relationships can adequatly handle
this situation without the other.
With the start-to-start relationship the editing will finish before the
writing which does not work.
If the finish-to-finish is used this is not a problem but then the editing
is starting much later then it has to. If for some reason the editing takes
longer then expected, or the editor is forced to spend time on something then
editing will finish later then it had to.
Any thoughts?
Thanks,
Scott Hanebutt
scenario and would like to know how it should be handled.
Sopose someone is writing a book and someone else is editing it and that
editing it will take 1/2 as long as writing it does.
Obviously you can't start editing until you start writing making it a
start-to-start relationship. Just as obviously you can't finish editing
until you finish writing making it a finish-to-finish relationship.
It seams to me that neither one of these relationships can adequatly handle
this situation without the other.
With the start-to-start relationship the editing will finish before the
writing which does not work.
If the finish-to-finish is used this is not a problem but then the editing
is starting much later then it has to. If for some reason the editing takes
longer then expected, or the editor is forced to spend time on something then
editing will finish later then it had to.
Any thoughts?
Thanks,
Scott Hanebutt