Girija
I have created a Master Project and inserted 2 projects related to two
departments. Now I want the project dates to be aligned based on the " Must
Finish On" Constraint, which is given to one of the activties in the Master
Project. This activity for which the constraint is given, has predecessor
from the Departmental activity with FF Task Dependency.
Dates are not aligning as desired, but the task date to which the constraint
is given changes without changing the other related tasks. What might be the
problem? I am using 2003 version. Does realignment take place when the
constraint is given to tasks which are linked to tasks in the inserted
projects?
departments. Now I want the project dates to be aligned based on the " Must
Finish On" Constraint, which is given to one of the activties in the Master
Project. This activity for which the constraint is given, has predecessor
from the Departmental activity with FF Task Dependency.
Dates are not aligning as desired, but the task date to which the constraint
is given changes without changing the other related tasks. What might be the
problem? I am using 2003 version. Does realignment take place when the
constraint is given to tasks which are linked to tasks in the inserted
projects?