Tasks are built in the 2007 ms-project tool that have multiple resources
assigned
Current Situation
------------------------
In many circumstances we may get only one or two of these resources
reporting progress in a week, meaning one or two have started working on the
task and report progress, but not all of them
Problem
------------
When progress is not taken against all resources, and less than all of them
have started working on it, ms-project 2007 results in scheduling errors when
this situation is resource leveled. The task will be unable to schedule
accurately and results in ms-project assigning thousands of hours (where
there should be at most a couple of hundred) to the remaining work when it is
unable to level successfully - no errors.
Remedy
------------
To fix this problem today I take one of two actions
a) assign some level of progress to the all the resources on the task wether
they actually started or not, if everyone is reported as having started then
project schedules just fine
b) break the task up into multiple tasks with each task having a one to one
relationship between the task and the resource assignment
assigned
Current Situation
------------------------
In many circumstances we may get only one or two of these resources
reporting progress in a week, meaning one or two have started working on the
task and report progress, but not all of them
Problem
------------
When progress is not taken against all resources, and less than all of them
have started working on it, ms-project 2007 results in scheduling errors when
this situation is resource leveled. The task will be unable to schedule
accurately and results in ms-project assigning thousands of hours (where
there should be at most a couple of hundred) to the remaining work when it is
unable to level successfully - no errors.
Remedy
------------
To fix this problem today I take one of two actions
a) assign some level of progress to the all the resources on the task wether
they actually started or not, if everyone is reported as having started then
project schedules just fine
b) break the task up into multiple tasks with each task having a one to one
relationship between the task and the resource assignment