bostonmeche
Hello,
I have 3 resources that I have assigned to a task. The task Work is 60 days
and so 20 days Duration is applied to each resource. The problem I have is
when I level the resources, Project still requires that each resource works
20 days on the task. I would prefer that if one of the 3 resources was too
busy that the other two resources covers for the busy one. This would mean
that the two resources do all or atleast a majority of the work. Is there a
way to have Project automatically assign the work to the free resources and
call the task complete? I believe the current setup is causing artificially
long project times. Thanks!
I have 3 resources that I have assigned to a task. The task Work is 60 days
and so 20 days Duration is applied to each resource. The problem I have is
when I level the resources, Project still requires that each resource works
20 days on the task. I would prefer that if one of the 3 resources was too
busy that the other two resources covers for the busy one. This would mean
that the two resources do all or atleast a majority of the work. Is there a
way to have Project automatically assign the work to the free resources and
call the task complete? I believe the current setup is causing artificially
long project times. Thanks!