Debbie Stein
I have a situation where I have 2 resources assigned to one task. They both
enter their actuals, and I ask that they each enter the work they have
remaining individually for that task. I expect that when I accept their
updates, Project will assign the remaining work to each resource individually
(ie. what each of them entered). What appears to be happening is that we can
not enter remaining work at a resource level. The remaining work that a
resource enters goes at the task level, and overwrites any remaining work
that another resource entered - it does not add to it. This is a big problem
for us. Is this how it is supposed to work or have we configured something
improperly? Thanks.
enter their actuals, and I ask that they each enter the work they have
remaining individually for that task. I expect that when I accept their
updates, Project will assign the remaining work to each resource individually
(ie. what each of them entered). What appears to be happening is that we can
not enter remaining work at a resource level. The remaining work that a
resource enters goes at the task level, and overwrites any remaining work
that another resource entered - it does not add to it. This is a big problem
for us. Is this how it is supposed to work or have we configured something
improperly? Thanks.