Multiple updates to the plan.

X

xlsstudent

Hi,

I have a complex plan which needs updates from atleast 5 different managers.
How can I colloborate with them? The plan is very complex and I dont want any
managers to delete any line items or insert one, ut just key in the actual
dates. Pls let me know if any best practices, tips tricks etc.
 
A

ahelp

You're kind of caught between a rock and a hard place. If the managers can
open the project and change dates, they can also add/delete tasks. There is
no way to lock it down that way. Your choices are procedures and training, or
copy & paste the tasks with dates into a spreadsheet & pass that around.
There's still risk they'll change that so you can't simply copy & paste it
back. Oh well.
 
J

Jim Aksel

Put everyone together in the same room and put the schedule up on the wall
with a projector. May the best personality win.
--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 
A

ahelp

A friend gave a PMI presentation on a like concept--called it a
"Decision-makers Conference" A variation I've heard is to give everyone a
large glass of water and declare, "No breaks until we're done!"
 