C
CNR OPS
Steps away from purchasing Project and I am concerned about the ability to lock out users from changing data. Want select users to input data, such as resources, materials, and equipment but not have the ability to change the start, duration, or finish date. Bottomline: is the software capable of setting security levels within a main project or should I consider implmenting several supporting projects feeding a main project that shares it pooled resources????