I have a project 2003. What is a restriction "must" in a first activity?
J John Nov 22, 2006 #2 kakos said: I have a project 2003. What is a restriction "must" in a first activity? Click to expand... kakos, What exactly do you mean by "must". There are many possibilities and without further information we would only be guessing. John Project MVP
kakos said: I have a project 2003. What is a restriction "must" in a first activity? Click to expand... kakos, What exactly do you mean by "must". There are many possibilities and without further information we would only be guessing. John Project MVP
J Jack Dahlgren Nov 22, 2006 #3 It means that the column is not wide enough to display the entire constraint type. It could be either Must start on or Must finish on. -Jack Dahlgren
It means that the column is not wide enough to display the entire constraint type. It could be either Must start on or Must finish on. -Jack Dahlgren
K kakos Dec 11, 2006 #4 Thanks Jack -- kakos "Jack Dahlgren" escreveu: It means that the column is not wide enough to display the entire constraint type. It could be either Must start on or Must finish on. -Jack Dahlgren Click to expand...
Thanks Jack -- kakos "Jack Dahlgren" escreveu: It means that the column is not wide enough to display the entire constraint type. It could be either Must start on or Must finish on. -Jack Dahlgren Click to expand...