I have received a Project file with several summary tasks. On a couple of
the summary tasks I have a cost, but the subtasks don't have any cost, and
there are no resources assigned to any of the subtasks, nor the summary. The
summary cost should be zero, but there is a value there. I cannot delete it
or change it (because it is calculated, I suppose), and I can't figure out
where the value is coming from.

Any suggestions?

TIA
 
J

Jack Dahlgren MVP

Which version of project?
There was a bug in older versions of project which summary tasks retained
costs of deleted subtasks.
The solution was to create a new summary task and delete the old one.
Note that you can not delete a summary task without affecting the subtasks,
so you need to outdent the subtasks first, then you can delete the summary.

-Jack Dahlgren
 
J

Jim Spiller

If Jack's response doesn't fix it try inserting "Fixed Cost" as a column and
zeroing out any costs for your summary tasks.
 