hi all
Becuase there is no summey tasks in 'My Task' views I created a text field
that goes to the assignment level so i will know to which module the task
belong.
The problem is that Once the resource reported some information about the
assignment the data in the field disappear.
Any thoughts ?
Becuase there is no summey tasks in 'My Task' views I created a text field
that goes to the assignment level so i will know to which module the task
belong.
The problem is that Once the resource reported some information about the
assignment the data in the field disappear.
Any thoughts ?