We've got a situation where when a user goes to My Tasks, several of
there projects have assignments that have a single strike through
across all columns. What is this generally caused by? What caused
them to notice this was that the timesheet entries wouldn't import
into the task correctly.

Thanks,
Andy Novak
UNT
 
M

Marc Soester [MVP]

Andy the strikethrough indicates that the user has deleted the task within
My Task
Hope this helps
 