N
nasir.khan
Is there any way for a resource to determine how many hours then have
entered for a given day in the "My Tasks" view?
The problem I'm running into is that resources were used to MSP2003
where the grid view allowed them to determine if they have accounted
for their entire day in project server - the new system does not seem
to have similar functionality in the "My tasks" view.
Is there any way to modify the "My Tasks" view or create a new view
that would provide comparable functionality?
Our organization is project based so we need the time to be submitted
to PMs for approval therefore timesheets won't work for us.
Thanks,
Nasir
entered for a given day in the "My Tasks" view?
The problem I'm running into is that resources were used to MSP2003
where the grid view allowed them to determine if they have accounted
for their entire day in project server - the new system does not seem
to have similar functionality in the "My tasks" view.
Is there any way to modify the "My Tasks" view or create a new view
that would provide comparable functionality?
Our organization is project based so we need the time to be submitted
to PMs for approval therefore timesheets won't work for us.
Thanks,
Nasir