Hello,

What is the best practice for resources indicating their tasks are blocked
in the "My Tasks" page? For example, if the task is scheduled to start on
9/30 for 5 days but the resource knows he/she won't be able to start the task
until 10/6, what is the best way to indicate this?

Thank you for your time,
Kevin
 
D

Dale Howard [MVP]

Kevin --

I would recommend any of the following:

1. A personal visit, a phone call, or e-mail to the project manager (good
human communication).
2. A Note on the task indicating the new likely Start date.

The resource can also modify the planned Start date of the task, but
frankly, I don't really recommend that. If you want your team members to
adjust the Start date, I would recommend that you MANDATE that they add a
task Note to document the reason for doing so. Hope this helps.
 
K

Kevin

A personal visit? Is that still done? ... :).

Ok, was thinking that there might be some sort of checkbox, etc, that could
indicate a warning, but adding a note to the task also sounds reasonable.
However, I agree that communication is key here.

Thanks Dale,

Kevin
 