My Tasks View

T

Trisha

After we applied the updates to project server 2007
(http://support.microsoft.com/kb/953750) I now have several users that when
they click on 'My Tasks' the page loads but the tasks are not displayed (only
one column of blank cells) and in the lower left it notes 'Done but with
errors on page.'

Any ideas?

Thanks!
 
G

Gary L. Chefetz

T

Trisha

Clearing the cache worked. Thanks Gary.

Gary L. Chefetz said:
Trisha:

You may be able to clear this simply by clearing the browser cache on the
affected workstations. If this doesn't work, you may need to uninstall and
reinstall the web components.

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com
 
Top