MY TASKS

F

Frank J.

Project 2007 Server:

Would like ability to filter out tasks that are 100% complete from the "My
Task" view. I realize this can be somewhat accomplished by adjusting the
"Define Current Task" setting from the Admin screen. But this is not really
the solution I would like to see since it would have other implications.

Frank j
 
D

Dale Howard [MVP]

Frank J --

At this point, there is no way to filter out completed tasks on the My Tasks
page in PWA. The system will automatically hide completed tasks after the
10-day window passes, or any other window specified by the Project Server
administrator. This situation is certainly one reason why we would not want
to specify a window greater than 10 days for current tasks in Project Server
2007. Hope this helps.
 