S
Skip W
Currently using MSP 2003 & server. I need to determine if a project has a
baseline so at the enterprise project Flag3 I use the formula iff(Baseline
Duration > 0, True, False). This is causing changes to enterprise Flag3
settings and I don't know why. Is there a better way to simply determine if
a project is baselined and set a field at the project level?
baseline so at the enterprise project Flag3 I use the formula iff(Baseline
Duration > 0, True, False). This is causing changes to enterprise Flag3
settings and I don't know why. Is there a better way to simply determine if
a project is baselined and set a field at the project level?