Need help for setting up an approval hierarchy for Project Manager

T

Thillai

Hi,

In our organization, we have Project Managers who reports to Project
Coordinator

We want to set an approval hierarchy where if Project Manager changes
Baseline in any project then once he saves, it should go for approval to
Project Coordinator.

We have control in EPM for Baselining the projects as,

Project Managers can set baseline No: 6 to 10 and
Project Coordinator can set baseline No: 0-5

I think this will give you some direction for the solution.

Can you please suggest us the best way to do the same?

If you need any further details please revert back

Thank You!