First- my RBS looks like this
President - level 1
Company 1 - exec -level 2
Comany 1 - pm - level 3
Company 1 - Team Lead - but within PM group - level 4

Company 2 - exec -level 2
Comany 2 - pm - level 3
Company 2 - Team Lead - but within PM group - level 4

I had a published project had a task was assigned to team lead company 1,
then I removed Team lead company 1 and replaced them with company 2 team
lead, but the company 1 people can still see the project.
Why?
 
G

Gary L. Chefetz [MVP]

Cindy:

Please don't post the same question repeatedly. I answered your previous
post.
 
C

cindy.becken

I don't think I did this. If I look at the RBS it shows only the levels for
each company under that companies executive. Any other ideas?
 