K
kinetix
I'm working on a complex Federal design/build construction project that
requires owner review of multiple design packages prior to start of
construction. The entire construction schedule is dependent on their
review and authorization to proceed. The original schedule included time
for that review, but they are quickly falling behind and can't/won't
provide a projected remaining duration or completion dates. Once the
reviews have actually been completed, I can update the actual finish
dates, but until that point I need a clean way to reflect the delays to
keep the rest of the schedule from just slipping into the past. The way
I've come up with is to use a leveling delay on the successro tasks
which then zeros out when I enter actual dates. Any ideas. thanks
requires owner review of multiple design packages prior to start of
construction. The entire construction schedule is dependent on their
review and authorization to proceed. The original schedule included time
for that review, but they are quickly falling behind and can't/won't
provide a projected remaining duration or completion dates. Once the
reviews have actually been completed, I can update the actual finish
dates, but until that point I need a clean way to reflect the delays to
keep the rest of the schedule from just slipping into the past. The way
I've come up with is to use a leveling delay on the successro tasks
which then zeros out when I enter actual dates. Any ideas. thanks