Networkdays

O

Omar Ahmad

Hi all,

I need to calculate the number of working days for a 7 day work-week,
excluding holidays which I have listed.
Can anyone help, please

Ombaf
 
V

Vasant Nanavati

Perhaps:

=EndDate-StartDate+1-SUMPRODUCT((Holidays>=StartDate)*(Holidays<=EndDate))
 
O

Omar Ahmad

Vasant Nanavati,

Thank you so very much. You saved me a lot of worry and sweat. Many thanks
once again.

Ombaf
 
V

Vasant Nanavati

You're very welcome! Thanks for the feedback.


Omar Ahmad said:
Vasant Nanavati,

Thank you so very much. You saved me a lot of worry and sweat. Many thanks
once again.

Ombaf
 