Arno
Ha,
We have a problem with PS2K3 from one of our clients. We copied the database
to our system and the same error...
We open an existing project and add a new tasks en assign a resource to this
task. After that a republish assignments.
Nothing happens:
The Homepage will not tell the resource that he has a new task.
The Project Center will not list this new task (all the old tasks are
their).
My tasks will not list the task.
BUT:
The View Resource Assigments will tell that the user has this task!!!
The eventlog btw will not state an error
Anyone any idea?
regards,
Arno
We have a problem with PS2K3 from one of our clients. We copied the database
to our system and the same error...
We open an existing project and add a new tasks en assign a resource to this
task. After that a republish assignments.
Nothing happens:
The Homepage will not tell the resource that he has a new task.
The Project Center will not list this new task (all the old tasks are
their).
My tasks will not list the task.
BUT:
The View Resource Assigments will tell that the user has this task!!!
The eventlog btw will not state an error
Anyone any idea?
regards,
Arno