Milind
Hello
In a new file, with 40 tasks, total duration shown is 30.48 days. However,
when I add resources to a task, the figure changes to 30.35. The task is of
2 days, time based, to be finished in two days with two resources, why the
change in duration? Even if I remove the check mark or put it again on
Effort based, still the duration changes.
Milind
In a new file, with 40 tasks, total duration shown is 30.48 days. However,
when I add resources to a task, the figure changes to 30.35. The task is of
2 days, time based, to be finished in two days with two resources, why the
change in duration? Even if I remove the check mark or put it again on
Effort based, still the duration changes.
Milind