I use MS Project 2003 and Project Server 2003.
I want to make the week between Christmas and New Years as non-working
time...so I copied the base calendar to Project Calendar, made the days
between Chrismas and New Years non-working, and saved the new Project
Calendar. Then I went in Project Information and changed the project calendar
to the new Project Calendar. But I still have tasks starting and ending on
the new non-working days between Christmas and New Years.....what am I doing
wrong?