On the Home Page of the 2007 PWA, it keeps showing that I have "xxx new
tasks" - but these tasks are old. In the 2003 version, once you logged out
and came back in, the "new" message went away.

Anyone know when a new task is no longer "new"?
 
S

Scott Morrissey

Can you define "open them"? I've gone to the task list and gone out. Do I
need to post time to them? Do I need to edit the detailed task information?
All I know is that it doesn't clear the message like the 2003 version did.

Thanks.
 
M

Marc Soester [MVP]

Scott, the best idea is to simply try out the steps you have written down. I
believe once you have used the task ( open the detail tasks page, or entered
time or comment) it will not be a new task anymore.
 
A

Astro Boy

Scott, the best idea is to simply try out the steps you have written down.I
believe once you have used the task ( open the detailtaskspage, or entered
time or comment) it will not be anewtask anymore.
--
Marc Soester [MVP]
State Manager: EPMhttp://marcsoester.blogspot.com





- Show quoted text -

Marc (and others),

For what its worth, I have tested Marc's hypothesis, and he is
correct. A task is "new" until you go into Task Details or record time
in My Tasks against it.
 