Jason Trust
All,
I have setup a project and published to the Project Server so that each
large summary section of the project has been published with a different
manager (using the Republish and become manager means). However, when a
resource adds a new task under a specific summary task, it always goes to
the project owner. Have I configured my project incorrectly, or is this the
expected behavior for new tasks. I was hoping it would send the "manager"
of that portion of the project plan instead.
Any other alternatives that people have would be appreciated.
Thanks,
Jason Trust
I have setup a project and published to the Project Server so that each
large summary section of the project has been published with a different
manager (using the Republish and become manager means). However, when a
resource adds a new task under a specific summary task, it always goes to
the project owner. Have I configured my project incorrectly, or is this the
expected behavior for new tasks. I was hoping it would send the "manager"
of that portion of the project plan instead.
Any other alternatives that people have would be appreciated.
Thanks,
Jason Trust