Greetings,
When I open the Enterprise Resource Pool from Project Pro 2003 and make a
change (any change - rate, name, initials, add a new resource, etc...) and
save&close the file, then go and reopen the Enterprise Resource Pool, the
changes I made are not evident and the data is reverted to what it was
before.
I am doing this with an administrator account will full priviliges. What
could be worng? Thank you kindly for your help,
-Dave