Hi,
Yes, the resources are the issue. Mostly it is the staffing of the jobs
with tradesmen. But sometimes it is materials and tools such as concrete
forms or large equipment such as excavating equipment. I would never link
the task of one house to another. Well maybe I would do it just to identify
which job comes first. Imagine an asphalt contractor who shows up one day in
May to do the driveways after a winter of being idle. If he has 4 drives to
do and can only do three in one day, the last thing you want is for him to
do the three that will move in next month and leave the house that moves in
next week till tomorrow or worse yet three weeks from now, when he gets back
in your neighborhood. In this business, the value of being on-site to manage
things is underestimated, but a schedule that is not clear about these
things will only hurt you. If left to his own, he will simply take the
closest houses to the entrance to the subdivision.
Another example of why I might occasionally link tasks from several houses
follows: In the context of large subdivision work I have in the past had
issues where a subcontractor will "Jump" onto a house that was ready for his
phase of the work, but my experience tells me that if I have two or more
houses that are close to having the same schedule and they get out of order,
it takes the might of several strong horses to regain control of the
schedule to get them back in the right order. (Yes this raises the question
of who's running the job.) In the residential construction world, everyone
wants to do the first available work and thus it becomes a matter of follow
the leader (chronologically speaking). And there are many jobs where the
subs are running the job.

In these cases I might link certain tasks as F-S in order to aid in
establishing order.
I'm sorry if this thread is drifting off-topic (the one started by
Prodilosso). We can carry if further in a new thread if you like.
John Hansen