I
Iliana Kostova
Hi all
I have the following problem with MS project .mpp - PWA cooperation
I've defined a new task and assigned it to an employee, who is present in the enterprise resource pool. On calling Collaborate -> Publish -> New and Changed Assignments, I get a message that the project is to be saved. After I OK the message, I receive another one, prompting me to confirm if I want to notify resources who have been removed from task assignments. I say OK again.
Then nothing happens - the employee does not have the task assigned in PWA, though the task is present in the PWA's project list
On re-publishing the project, the situation got even worse - now none of us can see assignments from the project
Any help on solving this problem will be greatly appreciated.
I have the following problem with MS project .mpp - PWA cooperation
I've defined a new task and assigned it to an employee, who is present in the enterprise resource pool. On calling Collaborate -> Publish -> New and Changed Assignments, I get a message that the project is to be saved. After I OK the message, I receive another one, prompting me to confirm if I want to notify resources who have been removed from task assignments. I say OK again.
Then nothing happens - the employee does not have the task assigned in PWA, though the task is present in the PWA's project list
On re-publishing the project, the situation got even worse - now none of us can see assignments from the project
Any help on solving this problem will be greatly appreciated.