When I log into Project Web Access and click the Tasks link/tab, before my tasks are loaded I get a VBScript error message box saying
"No periods have been defined after the current period. Contact your server administrator for more information." This happens in all views. Any ideas??

Thanks
 
D

Dale Howard

SI --

Your Project Server administrator simply needs to set up reporting periods
in PWA to make this warning message go away. You are not the source of this
problem. Hope this helps.




SI said:
Hi,

When I log into Project Web Access and click the Tasks link/tab, before my
tasks are loaded I get a VBScript error message box saying:
"No periods have been defined after the current period. Contact your
server administrator for more information." This happens in all views. Any
ideas??
 