No work for resources

N

Noël Thoelen

When i check the resources tab the actual values are always 0. Altough some
values do exists. Is it possible as a manager to enter the actual values for
your people using this feature. How could i see the planned work in that
case ?
 
D

Dale Howard [MVP]

Noel --

The Actual Work values need to be entered in PWA by team members and then
updated into the Microsoft Project plan by the project manager. After the
updating process, the project manager must also click Collaborate -
Publish - All Information to "push" the latest schedule changes to PWA. The
alternate method is to enter the Actual Work for each resource in the
Microsoft Project plan, but the PM must still click Collaborate - Publish -
All Information when finished. Hope this helps.
 