G
G Lykos
Greetings again! When work has never been assigned to a resource on a
particular day that the task usage view shows no value for that day.
However, it appears that once work is assigned, it can then be zeroed out,
but I can't figure out how to blank it out (meaning restoring it to the
original state before work was assigned, where it wasn't zero on a
particular day but rather was nothing, blank). Anyone know how?
Thanks,
George
particular day that the task usage view shows no value for that day.
However, it appears that once work is assigned, it can then be zeroed out,
but I can't figure out how to blank it out (meaning restoring it to the
original state before work was assigned, where it wasn't zero on a
particular day but rather was nothing, blank). Anyone know how?
Thanks,
George