Non-Project Project Plan Template

M

Melissa

Hi. Does anyone know of any links to good examples of non-
project time project plans? I don't want to recreate the
wheel. Thanks.
 
G

Gary L. Chefetz \(MVP\)

Melissa:

This a wheel that takes only a few minutes to invent. My best advice to you
is to keep it simple. Create a 2 to 4 tasks in a project plan. Make the
tasks fixed work. Set the duration to a quarter, half-year or year according
to your preference. Assign all your resources to the tasks at either 0% or a
low percentage according to your resource planning scheme. If you have a
very large resource pool, consider making a separate plan for each
department.

--

Gary L. Chefetz, MVP
"We wrote the book on Project Server
http://www.msprojectexperts.com

-
 