I've been struggling with this for a couple of days, and here's my
dilemna...
I created a project (well, several iterations) called "Non Project Time"
(after using various flavors of Admin). The Task hierarchy is as follows:
Non Project Time
Vacation
Resource 1 Assigned to: Resource 1 with
80 hours
Resource 2 Assigned to: Resource 2 with
80 hours
Etc Etc
Holiday
Resource 1 Assigned to: Resource 1 with
104 hours
Resource 2 Assigned to: Resource 2 with
104 hours
Etc Etc
Sick / Personal Etc
When I publish the project, the Assignments do not show on the timesheet
(with the All Tasks view), nor can I assign the task to myself as a resource
(since it is allegedly already assigned). The assignments are made against
Enterprise resources (as retreived from the server), and SOME task
categories show in View Timesheet Summary (Bereavement, Civic Duty), but
Vacation, Holiday, Sick/Personal, and Training all show as the assigned to
Resource. View Resource Assignments shows all Non Project Time tasks as
Resource 1, again with no reference to the summary task.
All categories were created the same way, with the same options set as you
suggested below. It is also disturbing that I am seeing "You have no changes
to update into Project." under updates on Home PWA, implying it is not
recognizing the Enterprise resource assignment. Changing the task name made
NO difference (in case it was a string match thing).
All other projects Import / publish fine.
Ideas?