A
Almoje
I am using MSP2007 for several projects en use a resource planning. The
problem I have is that
1) the people have 8 hour working days but are not working 8 hours on the
project. I can simply change the working time per person (it is different per
group) but when I ad vacation as a task (next problem) MSP is not using the 8
hours but the adjusted time. This means that the vacation days are shorter
than actual.
2) how can I use the non working time and make it visible in the Gantt
Chard, like individual vacation and the non project time per day.
3) when adding vacation in the resource information - change working time, a
task will not be split during the vacation time. Is this possible?
the idea is to easily show the resource work load and availability per day
thank you
problem I have is that
1) the people have 8 hour working days but are not working 8 hours on the
project. I can simply change the working time per person (it is different per
group) but when I ad vacation as a task (next problem) MSP is not using the 8
hours but the adjusted time. This means that the vacation days are shorter
than actual.
2) how can I use the non working time and make it visible in the Gantt
Chard, like individual vacation and the non project time per day.
3) when adding vacation in the resource information - change working time, a
task will not be split during the vacation time. Is this possible?
the idea is to easily show the resource work load and availability per day
thank you