"non-published" in OLAP cube?

L

Laura

Hi,

Is there a way to expand the OLAP cube to include project
schedule date that is another version (not just
published)?

What I am wanting to do is create a "Reserved" schedule
to prebook resources and have it show up in the OLAP cube
combined with "Published" version too.

Thank you for your insight and help!

Laura
 
D

Dale Howard [MVP]

Laura --

Has your Project Server administrator created a Version called Reserved? If
so, you can open your project, click File - Save as, and then selected the
Reserved version. The Reserved version data will appear in the OLAP cube
after the next build. Hope this helps.
 