Non Working day not showing in Gantt Chart

C

Cazzy123

Hi I have made a copy of the standard calendar and in the copy calendar under
Change Working Time I have added a couple of Non Working days. They show up
as an 'exeption day' in calendar here but when I look at the date in the
gantt view it is still showing as a working day.

I have checked under the Project properties that the Copy Standard calendar
is being used.

Has anyone any idea as to why it is not showing in the Gantt Chart.

Thanks
 
S

Steve House

The Gantt chart non-working time display can be controlled by any base
calendar you choose and is set indepedently of the Project Calendar setting.
To have your customized calendar control the non-working day display, right
mouse-click on the timescale, choose "Timescale," select the Non-Working
Time tab, and set your desired calendar as the controlling calendar from the
drop-down box.
 
C

Cazzy123

That works a treat, thanks Steve

Steve House said:
The Gantt chart non-working time display can be controlled by any base
calendar you choose and is set indepedently of the Project Calendar setting.
To have your customized calendar control the non-working day display, right
mouse-click on the timescale, choose "Timescale," select the Non-Working
Time tab, and set your desired calendar as the controlling calendar from the
drop-down box.
--
Steve House
MS Project Trainer & Consultant



.
 
B

Benoit Lhote

Thank you Steve.
It works also for me, it helps..

In fact I have a related need and a related question to solve:
- I would like to display Non-Working Time (let's say NWT) in Gantt view

a) first need, "NWT" defined in Calendar associated to current project
-> that's the aspect covered by Steve's answer -> ok, solved !

b) second need, "NWT" defined in a resource calendar; for example, let's say that "Ben" will not work on next Monday,
My context: I manage projects with several resources and it would be a help to visualize the non working time of people on same Gantt view than the overall project.
I agree that my need is not completely well formed, as I expect a mix between global info on project WITH personal info on a given person.
Your ideas are welcome....
Best Regards
Ben,







Steve House wrote:

The Gantt chart non-working time display can be controlled by any basecalendar
21-Nov-09

The Gantt chart non-working time display can be controlled by any bas
calendar you choose and is set indepedently of the Project Calendar setting
To have your customized calendar control the non-working day display, righ
mouse-click on the timescale, choose "Timescale," select the Non-Workin
Time tab, and set your desired calendar as the controlling calendar from th
drop-down box
-
Steve Hous
MS Project Trainer & Consultant

Previous Posts In This Thread:

Non Working day not showing in Gantt Chart
Hi I have made a copy of the standard calendar and in the copy calendar unde
Change Working Time I have added a couple of Non Working days. They show u
as an 'exeption day' in calendar here but when I look at the date in th
gantt view it is still showing as a working day

I have checked under the Project properties that the Copy Standard calenda
is being used

Has anyone any idea as to why it is not showing in the Gantt Chart

Thanks

The Gantt chart non-working time display can be controlled by any basecalendar
The Gantt chart non-working time display can be controlled by any bas
calendar you choose and is set indepedently of the Project Calendar setting
To have your customized calendar control the non-working day display, righ
mouse-click on the timescale, choose "Timescale," select the Non-Workin
Time tab, and set your desired calendar as the controlling calendar from th
drop-down box
-
Steve Hous
MS Project Trainer & Consultant

That works a treat, thanks Steve"Steve House" wrote:
That works a treat, thanks Stev

:


Submitted via EggHeadCafe - Software Developer Portal of Choice
ASP.NET Scrollable Table Server Control
http://www.eggheadcafe.com/tutorial...436-9d08c7fcda74/aspnet-scrollable-table.aspx
 
J

JulieS

Hello Ben,

You can display the nonworking time for a specific resources as the
background of the Gantt chart view through Format > Timescale. If the
resource's calendar is based upon the project calendar, it will show
nonworking time from both the project calendar and any exceptions
specific to the resource's calendar.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
Top