Non-working work week

R

RVE

Is there any way to make an entire week a non-working work week? As
in, a task is going to take 25 days, but the 4th of July occurs in the
middle and you want to show that during that week (or 2), no work will
occur. Besides creating a new task or extending the task during.
Thanks in advance!
 
D

DavidC

Hi RVE,

Open up the calendar, "Tools", 'Change working time..', then simply select
the days you want as non working. Make sure that the calendar you change is
the Project calendar and is the basis for all other calendars such as
individual resource calendars.

Hope this helps

DavidC
 