Nonproject time

M

Mark Heggestad

We've moved to using administrative projects in 2003, however the nonproject catagories are still in everyones timesheet, how to I remove them as an administrator? Do I just simple tell everyone to hide them?

Mark
 
D

Dale Howard

Mark --

Are the nonproject time categories appearing from your former Project Server
2002 installation, which you upgraded to Project Server 2003? Or are the
nonproject time categories coming from the administrative projects in
Project Server 2003?

If they are the former, I believe that your people can hide them, as they
are not needed. If they are the latter, you people should not hide them as
they will need to enter actuals into the various categories. Hope this
helps.




Mark Heggestad said:
We've moved to using administrative projects in 2003, however the
nonproject catagories are still in everyones timesheet, how to I remove them
as an administrator? Do I just simple tell everyone to hide them?
 