I'm using Prohect Web Access & Project professional 2003.
Is there any method for not allow to enter actual work in completed task
from resource time sheet.There is a Filter option in PWA 2003 for showing
only Un completed task but this is only filter between completed and
uncompleted tasks.
Please help me.