not seeing detail of sub project

M

Monica

I have enabled sub projects in Project Server's Admin
area, and published a master project and a sub project.
However, I cannot see the tasks or sub tasks of the sub
project from within Project Server. The entire sub
project is represented as one line only in the master
project. Any ideas? Can Project Server in fact display a
full detailed view of a master project and all its sub
projects? (I understand that time entry will be doubled
with this approach; willing to live with that for now.)
 
A

Ahmad

Hi Monica,
Something like that happened to me, but I am not using Master Projects.
Check the Event Viewer for DCOM errors 1004, & 1002; if so use PSCOMPLUS and
change the DCOM service identity.
I hope this would help,

Regards,

Joe Black
EPM Consultant
 